Mining Information Services Limited


A Discussion of the Parameters Affecting the Construction and Maintenance of Quarry Haul Roads

Dr Jack Mills
Eur Ing C.Eng. PhD. FIQ. FIMM. FIExpE


Haul Roads

The following paper is a general description of haul roads found within a typical overseas [tropical] quarrying environment. As the examples are all overseas, they take no recognition of UK legislation, whether applicable or not. A lack of suitable haul roads can lead to the situation shown in figure one where a fully loaded Cat 769 dump truck was driven off the side of a narrow road. The road was the exact width of the vehicle and passed through a residential area, luckily, the driver was unharmed. The next day, another driver (also unharmed) did exactly the same thing, in the same place and almost destroyed a house, proving the point that for some company's, lessons are learned the hard way.


Definition


This paper defines the quarry as the place from where the stone is won, not the process area, unless they are one and the same place. Quarry haul roads can generally be categorised under one or more of the following headings;


  1. Access or exploratory road, these roads or tracks are often used to either explore or give access to the area above or beyond the quarry benches. The standard of construction will be basic. The use of access roads is usually limited to tracked vehicles, such as excavators, dozers and drilling rigs. If the roads are intended for general use, then they must be constructed to the same standards as the bench access roads.

  2. Bench access road, if the quarry is designed correctly, this road, will provide a permanent main access into the quarry and service all the quarry benches and beyond. It may have feeder roads leading from it to each bench level. The bench road should remain for the life of the quarry, be designed and constructed for mixed use and maintained to a high standard.

  3. Main haul road, this road usually extends from the quarry area and links the bench access road to the process plant. The main haul road is likely to be remain for the life of the operation and will be used by all types of vehicles including road vehicles and high speed and heavy dump trucks. The road must be designed, constructed and maintained to a very high standard, including all the safety features that would be found in a major highway.

Design


Each of the above will have its own design priority and criteria, time and effort spent in design will always save money later on, unfortunately the regime of cash flow found when developing a quarry often calls for minimum expenditure at the outset. Although useful at the start, cost cutting in design usually cost much more later on when the road has to be moved. The use of modern surveying equipment and dedicated computer design packages enables a quarry to be designed at the planning stage and the design carried through until the resource is exhausted and the site closed. It is much more cost effective to design the road with planning software than it is to keep physically removing and rebuilding it. At this time, the planner can place the road in the quarry, view rapid changes of direction or other route changes for optimum arc of visibility and measure gradients. The design should consider inclines, whereby the maximum slope value should be not more than 1 in12, however in areas where this is not attainable, the road must be designed to enable a gradient no steeper than 1 in 10 to be achieved, and this, only to be used by suitable vehicles operating within their design criteria. The bends should be near horizontal and well drained. At design stage it should be remembered that bends and acute changes in gradient cause the trucks to brake and accelerate, both these actions waste energy, both increasing operating costs and causing environmental damage with excessive noise and fuel smoke.


Access road


The road with the least design requirement will be the access track, this may only be a path dozed over or through the overburden. Its life may only extend to the full development of the benches, at which time, a more permanent road would be constructed. The design should be sufficiently detailed to facilitate an upgrade as required. Even though this road will only be used on occasion, it should generally comply with the requirements of the main haul roads, both in design and construction, particularly with regard to safety and the environment. If it is only to be used by tracked vehicles, the management may mitigate the costs of design and construction by accepting a lower standard of surfacing, drainage, width and slope values, all providing that the track conforms to local legislation and remains safe to use. The road shown in figure three displays extreme slope values, blind corners and complete lack of drainage, these factors caused many accidents.


Bench road


This road should preferably, be designed at the preliminary stages of quarry planning, and if possible it should provide access to every area of the developing quarry. Usually this is achieved by constructing the road at one end of the benches, from which each bench is developed. As this is to be a semi permanent road, more time and funding should be made available at design and construction to get it right first time. Constantly repositioning and repairing the road is costly and can confuse the drivers. This road is likely to require the greatest slope values as it extends to serve all of the benches. To accommodate changes in the quarry or mitigate the slope values the road may be designed with looping and "switchbacks" or it may travel alternately across each of the benches. Figure four shows a well designed bench road being used by a Cat 777 dump truck, the road is more than wide enough to accept three times the width of the largest vehicle that uses it, and the driver has a wide arc of vision. The bend or switchback has been cut to be horizontal, dust suppression has been provided by a water spray.


Main Haul road


This is the main artery between the quarry production area and the process plant. In the UK this may be one and the same area, however. In larger quarries or open pit mines the haul route may extend several kilometres. As this road is likely to be in existence for the whole life of the project it is wise to design and construct it to a high standard. At initial design stage, maximum efforts should be made to ensure that the road will have a minimal environmental impact, both during construction and use. In Jamaica and other Caribbean countries the maximum footprint of the quarry is restricted, and the whole length of the haul road is considered as being part of the quarry. It is often forgotten that the surface area of a haul road can often be larger than that of the benches and quarrying area. Figure five shows a main haul road used by Cat 769 dump trucks feeding limestone to a kiln in Zambia, although well designed, the road is suffering from a lack of maintenance with the drains becoming filled and overgrowth. It is interesting to note that at this site the main slope into the quarry was sealed with concrete, making the surface all weather and reducing tyre wear.

It is not always possible to design a road to theoretical perfection with moderate inclines and bends having a zero gradient. The responsibility for design and construction of the road shown in figure six was given to the writer following the death of the quarry manager during initial construction. Due to the requirement to climb two hundred metres in one thousand, the task was at first considered to be impossible, eventually a road design and constructed that had four switchbacks. The road was used without serious incident by Cat 250 articulated dumpers, the fact that there was not a serious accident was due more to the quality of the drivers than the design. Constructing roads as shown with high gradients and acute bends is not recommended.


Construction


This section does not intend to constitute a working plan of construction but is intended as a guide to the general layout of haul roads.

The road should be constructed to a standard, probably comparable with a heavy duty highway and its construction should follow conventional techniques. The foundation upon which the road is constructed is of significant importance.


If the road is following a reasonably level terrain, then for drainage purposes it must be elevated. In this instance construction would begin with an excavation to either suitably solid ground (sub formation) or if this is found to be plastic (clay), then a surface membrane and unbound fill material would be used to ensure a suitable bearing ratio was achieved. Further construction of compacted fills would be layed with the final surface being sealed. Although as is often the case, solid rock is not considered as a suitable surface for a haul road, this is because of difficulty in achieving the correct contour, its lack of draining ability and general poor grip due to polishing. Also, a clean rock surface can in some instances provide a slip plane between itself and the rock fill, this may cause the road to fail at points of high lateral force. The interface could possibly allow water to pass, this would ultimately wash away the fines in the fill, reduce the compaction by introducing voids and ultimately destabilise the construction. Generally, it is much better to blast the rock, cut to profile, build with suitable fill and compact. The sub surfacing should be compacted to a value suitable for the projected dynamic loading, which are especially severe during braking.

Depending on the duty required from the road it may be necessary to seal the surface, this can be a graded surfacing of roadstone, concrete, asphalt, or "chip and spray". Sealing the road will prevent the ingress of water, aid drainage, reduce drag and therefore improve fuel consumption, reduce noise and dust.


Drainage


Building a road without drains is pointless, water entering the road will cause the fill material to effectively loose specific gravity (being suspended by the water), will lubricate the fill material thereby reducing friction and enabling it to become displaced under load, will wash away the fines, thereby leaving voids and will wash away the surface material.


Unsealed roads are often designed to have a super-elevation or cross fall, (meaning the surface will always fall in one direction at any particular location, the fall will be in the direction of the highest terrain (see figure eight). It is important for the surface water to remain as sheet flow (not turbulent), to accomplish this, calculations must be made for the expected maximum rainfall and the slope value of the surface designed accordingly. A typical slope value will be about 2 to 5% anything greater will not only make the water to flow too fast, but will cause excessive tyre wear and side loading on the wheel bearings of the dump trucks. From the super-elevation the water will discharge into a longitudinal drain, possible using a membrane to prevent erosion. The drains must be designed with full consideration given to the maximum flow requirements and where required, geo- textiles and armour rock can be used to stabilise and strengthen the channel, the geo-textiles may need to be installed to prevent water from entering the road fill. A flow velocity of 1 m/s is the maximum rate suggested to control erosion in earthen drains, this is a maximum rate and for easily erodible soils the velocity should be reduced by the use of rock dams and slopes of less than 3%. The drain will terminate at a constructed culvert and usually a cross drain will carry the water beneath the road to a reinforced drop structure for dispersal. The cross drain should have sufficient diameter to allow cleaning (minimum 800 mm) and the drop structure will be designed to prevent erosion.


Designing a road with a super-elevation has the added advantages of ease of maintenance by a grader (only one profile) and the truck always being directed by gravity away from the side of the road that has the drop.


Road maintenance


Due to the constant volume of heavy traffic together with a relatively light, without maintenance a haul road will very quickly fail. Regardless of the surfacing, the road will require regular maintenance and repair.


The following maintenance activities are advised:


If the road is sealed using asphalt or chip and spray, then it is important to repair any holes that may develop, failure to carry out surface repairs will allow water to soak into the fill, destabilising the structure.


Environment Design


Measures for environmental mitigation should be considered and implemented at design stage. Much of the environmental nuisance can be mitigated by careful design, such as constructing as much of the road as is possible beneath exposed features, such as beneath the rim of a valley or shielded from sight by a hillside. The road shown in Figure six was constructed adjacent to the islands airport and gave the tourists their first view of the island, the visual amenity would have been improved by tree planting had the volcano not destroyed the site. Figure ten shows the effect of failing to put prevention measures into operation. In this instance, simply watering the road would have reduced the dust.


The main environmental areas of concern are likely to be;


A full study of all the above impact should have been completed at design stage at measures of mitigation incorporated into the design.


Safety


The quarry is a heavily restricted area and the haul road whether or not it is in the quarry will be subject to local legislation, normally, the only personnel authorised to use the haul roads should be;


To ensure road safety, the following recommendations may be considered;


Where required, (which is often the full length of the carriageway) the road should be fitted with substantial ARMCO safety barriers. The construction of berms often causes the truck to overturn and only the very largest boulders will be sufficient to prevent a truck from breaking through. ARMCO will reduce the impact and contain a vehicle without causing excessive additional damage. The driver of the Cat 966 shown in Figure eleven was out collecting firewood when he turned from the road, he survived without injury.


Dust Mitigation



The Haul road can be designed to place the maximum distance between dust production and sensitive areas. These sensitive areas can be protected by use of the topography, either natural, such as, woodland, or man made with the careful positioning of screens. The travelling distance of dust can be reduced by taking advantage of the direction of the prevailing wind and building screens to reduce wind velocity and if possible disruption in the form of vortices. Dust can be reduced by using a hard rock surfacing or preferably, coating the road with bitumen or asphalt, keeping haul routes as short as possible and reducing gradients. In addition, haul routes to waste dumps and stockpiles can be located in the lee of prevailing winds and away from sensitive locations, such as, residential locations, and main highways. Leafy trees can be grown at the sides of the road which will filter the air and trap the dust particles.


Noise mitigation


The technology is now available for a computer aided design to produce accurate noise modelling of site operations. The programme uses a three dimensional computer model of the topography and adjacent areas as a basis for undertaking automated noise calculations. The location of the haul routes together with details of noise prediction points are then added to the model. The contribution of noise from each item of plant and any haul routes, allowing for the attenuation of noise with distance and any noise reduction effects are then calculated for each point. These are then summarised to obtain the overall noise levels in terms of Leq.


The code of practice for basic information for noise control'. In particular, the following measures are commonly used;



Poor road maintenance or excessive use of "sleeping policemen" will not only cause damage to the vehicles but will create noise due to the trucks bouncing and the bodies slapping on the chassis.


Summary


The design, construction, operation and maintenance of haul roads may not be the most exciting part of quarrying, but they are vital to the safety and smooth operation of the business. Time and money spent in maintenance of the roads may not always give an immediate cash return, but cutting down on the maintenance will soon be converted into an increase in the cost of maintaining the trucks plus reduced production. This paper recommends that the roads are designed to last, are well constructed and maintained. If the roads cross public areas they will eventually either be absorbed into the local road network (as happens in Jamaica) or be removed and the land reassigned for other uses. Figure thirteen shows what can happen when it all goes wrong, this driver using safe wide roads and after considerable training survived an accident in a fully loaded truck that overturned at high speed.


Reference material; Jack Mills


A Technical Discussion of Mining Operations in the Lime and Cement Industries of Zambia and Malawi. A Doctoral thesis presented to The University of Nottingham.